18 ORMOND QUAY UPPER, DUBLIN 7

18 Ormond Quay Upper is a handsome example of a north-side merchant house sited on the north Liffey quays overlooking Christ Church Cathedral and the Civic Offices. It dates primarily from the 1840s but also incorporates building fabric of much earlier date.

The building was in very poor condition, being in a near state of collapse and was originally scheduled for demolition due to its poor condition when rescued by Dublin Civic Trust. Its conservation necessitated a very sensitive approach to conservation and structural stabilisation.

Acquired by Dublin Civic Trust in 2015, it represents not only a conservation project but an educational facility in which the conservation process is presented ‘live’ to students and practitioners through regular access opportunities, courses and seminars on building materials and conservation techniques – along with online charting of the entire process  comprising a series of conservation and restoration based seminars and talks presented by the Trust and has established a model for creative reuse and urban conservation that can be applied across the city.

Dublin Civic Trust appointed Kelly and Cogan Architects in late 2015 to deliver the first phase of its building conservation project to restore a residential home to the upper floors of Number 18 with an active separate shop to the ground floor. That phase of the works primarily comprised the structural consolidation and exterior refurbishment of Number 18.

Following stabilisation of the fabric, our appointment continued into the second phase of the works in 2017 with the internal conservation and refurbishment of interiors to Number 18 in collaboration with Graham Hickey – Heritage and Conservation Director of the Trust.

It should be added that Dublin Civic Trust’s engagement and expertise considerably enhanced this project and its outcomes.

The works have involved a major programme of structural consolidation and conservation of historic fabric.

The greatest challenge Number 18 faced was a significant structural destabilisation of the east facing gable wall which visibly bulged over Arran Street East.

This movement was caused by the removal of internal walls over the course of the 20th century and historic water ingress that rotted bonding timbers in the outside walls, encouraging outward movement. Poor original detailing also played a part, with insufficient brick bonding to adequately tie walls together.

An extensive laser survey of the front and side elevations was undertaken which revealed the precise locations of problematic areas. This enabled a structural strategy to be developed to reinforce and tie these areas into a new four-storey grid of steelwork applied to the inside face of the gable wall, anchored to the brick masonry with a series of stainless steel ties along the structural grid. In turn, this steel grid was tied back to the superstructure of the building with a series of metal ties and steel plates embedded in the spine and party walls. This approach enabled the complete omission of unsightly pattress plates to the exterior that would otherwise have been required.

The stone-arcaded shopfront at the front of the building, which likely dates to 1789 with the upper floors rebuilt above it in 1842, did not provide sufficient structural support for the building’s upper walls.

The arched granite stonework and infill masonry required additional engineering restraints to ensure the overall building was adequately supported and to prevent future outward movement. As part of these works, the side arch facing Arran Street East was reopened with its infill blockwork removed.

The original design intent of the shopfront had become obscured over time, with opes and entrances moved and the stonework painted over. These later interventions were reversed to reveal the original design.

Throughout the building, water ingress had resulted in significant decay of structural timbers including window heads and joist ends, all of which contributed to the near collapse of the structure and required intervention and reversal.

The two street facades were coated in a rough cement pebbledash finish in the 1950s which trapped rainwater  and concealed failing flat arches over windows, sagging window aprons and disfigured the elegant yellow brickwork.

The facades originally featured hand-wigged lime jointing, a sample of which survived beneath a former street sign, enabling replication following removal of the failing cement dash.

Internally, the original lime plaster finishes to walls and ceilings had experienced decay as a result of water ingress ranging from delamination of plaster layers to wholesale failure of plaster, all of which required stabilisation and repair.

Ceilings were patch repaired in lime and sagging surfaces tethered using  steel tie hangers, while in limited areas complete replacement where required was carried out using lath and lime plaster. Finally, breathable insulation strategies, including the use of Calsitherm Climate Board and Diasen Cork-Based Thermal Plaster, were used in vulnerable areas to improve the thermal performance of the building.

The works are now nearing overall completion with the final phase of the works, consisting of the interior and exterior conservation and refurbishment of the conjoined but separate 18th-century rear portion of the building at 67 Arran Street East which commenced in early 2020 and is scheduled for completion in 2022.

Details

Location

Ormond Quay Upper, Dublin 7

Date Of Construction

c. 1760 and 1843

Client

Dublin Civic Trust

Location: Ormond Quay Upper, Dublin 7
Date Of Construction: c. 1760 & 1843
Client: Dublin Civic Trust